Supplier of comprehensive solutions
for the utilisation od straw bales for power production

Be the First in Straw.

Reference BFS

Developer/Investor

  • Two completed projects
  • Value of projects 80 million

 

General supplier

  • Tried and tested technology
  • Custom-built design of automated transport of fuel to the boiler
  • Custom-built design of straw-burning boiler

 

Operator

  • Processing of fuel from the field to the boiler
  • 300,000 tonnes of straw/750,000 packages burned since 2008

 

Implementation


EC Jindřichův Hradec Ltd. 2007 - 2010 - completion of project

  • Source of combined production of electricity and heat by the burning of agricultural biomass
  • Investment of approximately €15 million
  • Maximum electrical output of 5,6 MWe
  • Maximum heat output of 15 MWt
  • Annual heat supply to customers of 160,000 GJ
  • Annual fuel consumption of 45,000 tonnes
  • Operations launched January 2009

 

EC Kutná Hora Ltd. 2009 - 2012 - General supply

  • Source of combined production of electricity and heat by the burning of agricultural biomass
  • Built on a green field
  • Investment of approximately €24 million
  • Maximum electrical output of 6,7 MWe
  • Maximum heat output of 15 MWt
  • Annual fuel consumption of 60,000 tonnes
  • Annual heat supply to customers of 140,000 GJ
  • First ignition 14 months after commencement of contruction
  • In operation from January 2012

 

EV Kutná Hora 2012 - 2013 - General supply

  • Hot water circuit source
  • Boiler 2x 10 MW
  • Investment of 5,5 million
  • Annual fuel consumption of 15,000 tonnes of fuel
  • Planned launching of operations in December 2013
BFS Energo, a.s.

News

01.07.2016

BFS realizuje generální dodávku elektrokotle 12MW pro účely regulace výkonové rovnováhy v elektrické přenosové soustavě

12.05.2015

Generální dodávka výtopny Kutná Hora spalujících biomasu ukončena. Výtopenské kotle 10, 6 a 2,5MWt předány do trvalého provozu.

07.05.2014

V průběhu března a května podepsány nové smlouvy na generální dodávku horkovodních kotlů 2,5MW a 6MW. Výstavba horkovodního přivaděče pro Kutnou horu finišuje.

Download

Energetické investiční celky Kutná Hora Komplex článku, který byl stěžejním tématem v časopisu All For Power - září 2013.